Campus Transformation Construction Update: November 2010

Campus Transformation Construction Update: November 2010

The West Pavilion construction is moving along this fall. A few current updates: Enabling Projects Phase, which includes utility relocation, is complete General Contractor Power Construction was selected as the General Contractor Construction zone is being secured with fencing Existing utilities are being marked Construction trailers are set up The Physician Entrance area is being…