Campus Transformation Project Construction Update May 2011

We’re excited to see the campus transformation project continue to move along. A few current construction updates:

Complete items:

  • Secure off-site parking for sub-contractors
  • Excavation and structural support of North Link
  • Construction of Interim Loading Dock
  • Precast brick selection
  • Caisson supports (151) complete
  • West Pavilion nurse call selected and approved
  • Flooring selected and approved

Currently in Progress:

  • Form and pour structural columns
  • Form and pour foundation walls
  • Form and pour south elevator pit
  • Water-proofing and drain tiles around foundation walls

The Campus Transformation Project is anticipated to be complete in 2014. The “West Pavilion” replacement patient tower plans include:

  • 96 Private Patient Rooms with Bath
  • Comprehensive Women’s Center for Life and Health
  • Pharmacy and Laboratory
  • Energy-Efficient Energy Plant
  • Gift Shop
  • Hospital Kitchen and Cafeteria

To follow the progress of Little Company of Mary’s Campus Transformation Project, sign up for our enewsletter or log on to www.LCMH.org/transformation.